Forecast the cost to complete
Track time and direct purchases against the project scope. Estimate the remaining effort using what the team now knows, not the original budget alone. Identify whether changes are client-requested, internally caused or part of the original promise. Discuss scope changes through the agreed commercial process before assuming extra work will be paid. A short weekly review of large projects can reveal problems earlier than a year-end margin report.
ILLUSTRATIVE EXAMPLE
Make it concrete.
A €15,000 project budgeted at €9,000 cost has €6,000 expected contribution. If €8,000 is already spent and €4,000 remains, expected contribution has fallen to €3,000 even before final invoicing.
Your action checklist
- Track actual and remaining hours
- Include subcontracting commitments
- Document scope changes and approval
A common mistake to avoid
Hours already worked are not the whole cost picture. Ignoring remaining work can make a troubled project appear profitable until it finishes.
Method & further reading
This practical article uses original illustrative examples and the explicit calculation or working method described above. It does not set a tax rate, legal deadline or universal performance benchmark. Read our editorial approach.
Bring the question to your accountant
Write down the period, the figures or documents you are using, and the decision you want to make. If a number is uncertain, show it as an assumption. You can use the linked tool to compare a scenario, or add the related service to your basket to request a scoped proposal.